Naval supply ship budget increase of almost $1 billion blamed on problems encountered building vessels, extra labour costs

Here's how construction costs of Royal Canadian Navy Joint Support Ships soared to $3.4 billion.

featured-image

Share this Story : Naval supply ship budget increase of almost $1 billion blamed on problems encountered building vessels, extra labour costs Copy Link Email X Reddit Pinterest LinkedIn Tumblr Breadcrumb Trail Links Defence Watch Naval supply ship budget increase of almost $1 billion blamed on problems encountered building vessels, extra labour costs Here's how construction costs of Royal Canadian Navy Joint Support Ships soared to $3.4 billion. Get the latest from David Pugliese, Ottawa Citizen straight to your inbox Sign Up Author of the article: David Pugliese • Ottawa Citizen Published Sep 19, 2024 • Last updated 6 minutes ago • 3 minute read Join the conversation You can save this article by registering for free here .

Or sign-in if you have an account. Earlier this summer, the federal government quietly announced that a contract awarded to Seaspan's Vancouver Shipyards Co. Ltd.



for two supply ships had grown by almost $1 billion. Photo by Seaspan / . Article content The difficulties encountered in building Canada’s new supply ships is behind much of the almost billion dollar jump in price for the two vessels, federal statistics show.

The actual construction of the two Joint Support Ships for the Royal Canadian Navy was supposed to cost taxpayers around $2.5 billion but last month the federal government revealed that cost had now jumped to $3.4 billion.

Advertisement 2 Story continues below This advertisement has not loaded yet, but your article continues below. THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY Subscribe now to read the latest news in your city and across Canada. Exclusive articles from Elizabeth Payne, David Pugliese, Andrew Duffy, Bruce Deachman and others.

Plus, food reviews and event listings in the weekly newsletter, Ottawa, Out of Office. Unlimited online access to Ottawa Citizen and 15 news sites with one account. Ottawa Citizen ePaper, an electronic replica of the print edition to view on any device, share and comment on.

Daily puzzles, including the New York Times Crossword. Support local journalism. SUBSCRIBE TO UNLOCK MORE ARTICLES Subscribe now to read the latest news in your city and across Canada.

Exclusive articles from Elizabeth Payne, David Pugliese, Andrew Duffy, Bruce Deachman and others. Plus, food reviews and event listings in the weekly newsletter, Ottawa, Out of Office. Unlimited online access to Ottawa Citizen and 15 news sites with one account.

Ottawa Citizen ePaper, an electronic replica of the print edition to view on any device, share and comment on. Daily puzzles, including the New York Times Crossword. Support local journalism.

REGISTER / SIGN IN TO UNLOCK MORE ARTICLES Create an account or sign in to continue with your reading experience. Access articles from across Canada with one account. Share your thoughts and join the conversation in the comments.

Enjoy additional articles per month. Get email updates from your favourite authors. Sign In or Create an Account Email Address Continue or View more offers Already a subscriber? Login If you are a Home delivery print subscriber, unlimited online access is included in your subscription.

Activate your Online Access Now Article content The extra labour costs, because of the challenges encountered in construction the ships, accounted for around $500 million of the increase, according to figures provided by the Department of National Defence (DND) to the Ottawa Citizen. “This is reflective of the challenges associated with building a large first of class warship,” DND spokesman Kened Sadiku said in an email. The increase in labour costs was “exacerbated by the effects of COVID on production efficiency,” he added.

Costs of material also increased because of the COVID-19 pandemic, adding another $260 million, he said. The rest of the almost billion dollar increase was because of foreign exchange rate fluctuations and adjustments to insurance fees because of the added time needed to build the ships, Sadiku said. Public Services and Procurement Canada (PSPC) confirmed to the Ottawa Citizen that it signed the contract amendment to give Seaspan — the company awarded the contract to build the ships — the extra money on July 19.

But department didn’t make that public until Aug. 2, the Friday before the civic long weekend. PSPC did not explain the reason for waiting until just before the long weekend to announce the significant increase in cost for the ships.

Advertisement 3 Story continues below This advertisement has not loaded yet, but your article continues below. Article content The additional construction fees means that the entire budget cost for the two ships is now $6 billion, up from the original estimate by DND in 2020 of $4.1 billion.

That budget includes additional infrastructure and project management. PSPC did not rule out further increases in costs. In an emailed statement from Seaspan, Leo Martin, senior vice president of programs at the shipyards, said the building of the first ship, HMCS Protecteur, has been challenging.

He blamed the increase in costs for the taxpayer on the pandemic, labour shortages, inflation and supply chain problems. The building of the two Joint Support Ships was supposed to cost taxpayers around $2.44 billion but last month the federal government revealed that jumped to $3.

4 billion. Photo by Seaspan / ott He noted the company is on track to launch the first ship this year. However, it won’t be delivered to the navy until next year, he added.

The second ship will be delivered in 2027 to the navy. But the problems and delays with the Joint Support Ship program started long before COVID-19. At one point, the first ship was supposed to arrive in 2012.

That has been changed a number of times with the government later hoping for a 2018 delivery and then a 2019 arrival for the first vessel. Then DND officials told the Ottawa Citizen in 2018 the first ship was expected in 2022 or 2023. Advertisement 4 Story continues below This advertisement has not loaded yet, but your article continues below.

Article content The construction of new ships for the Royal Canadian Navy have seen significant increases in costs as well as delays. The Canadian Surface Combatant (CSC) program, originally budgeted at $26 billion, has increased to at least $60 billion. DND officials insist the costs on that project to deliver 15 new warships will not go up further.

Critics have labelled the CSC project, the largest single purchase in Canadian history, as a bottomless money pit with little accountability or oversight. The first CSC was originally to be delivered in the early 2020s. In February 2021, DND admitted the delivery of the first vessel wouldn’t take place until 2030 or 2031.

The other key naval program is the Arctic and Offshore Patrol Ship project which is currently delivering vessels. But that project has also faced problems. Some of the vessels have been out of action because of ongoing mechanical failures or have had to return to port because of flooding.

Despite this, defence officials noted the key message to push to the public and news media was that the naval shipbuilding projects were a success, according to a 2020 briefing obtained by the Ottawa Citizen under Canada’s access to information law. Advertisement 5 Story continues below This advertisement has not loaded yet, but your article continues below. Article content The briefing written by Tina Raymond, a DND public affairs official, claimed that the negative views of the naval ship programs were because of problems associated with the building of non-military vessels for the federal government.

Projects being handled by DND “demonstrate good stewardship of public funds,” she added. David Pugliese is an award-winning journalist covering Canadian Forces and military issues in Canada. To support his work, including exclusive content for subscribers only, sign up here: ottawacitizen.

com/subscribe Recommended from Editorial Military procurement a success, says DND — MP questions whether the department has lost touch with reality Procurement chief at National Defence to step down Article content Share this article in your social network Share this Story : Naval supply ship budget increase of almost $1 billion blamed on problems encountered building vessels, extra labour costs Copy Link Email X Reddit Pinterest LinkedIn Tumblr Comments Join the Conversation Postmedia is committed to maintaining a lively but civil forum for discussion. Please keep comments relevant and respectful. Comments may take up to an hour to appear on the site.

You will receive an email if there is a reply to your comment, an update to a thread you follow or if a user you follow comments. Visit our Community Guidelines for more information. Trending Ottawa Senators owner Michael Andlauer drops game-changing hints over breakfast at Al's Diner Osman found guilty of second-degree murder in 2022 St.